1st stage of repair and rehabilitation works to the viaduct at km 61+327 on Trakia Motorway was completed
Consortium “Geostroy – Mostremont 97 – Patstroy 92” completed the 1st stage of repair and rehabilitation works to the viaduct at km 61+327 on Trakia Motorway
On 22 November 2013 Geostroy in consortium with Mostremont 97 and Patstroy – 92 executed the first stage of remedial works to Varshilata viaduct at km 61+327 on Trakia Motorway. The right roadway in the direction Sofia-Plovdiv was completely repaired. The rehabilitation works include construction of new sidewalk blocks, reconstruction of the existing drainage system and execution of new waterproofing. New protective systems were installed - crash barriers and guardrails. The entire roadway was covered with binder course and wearing course of asphalt pavement. New dilatation joints were mounted and horizontal thermoplastic road markings were applied.